Facility Construction Information

Mansard Resurface

Estimated Cost: $85,000
Funding Source: Special Assessment
Current Status: Complete.
Estimated Construction Time: July 15-August 16
Architect/Design Consultant: JHDesign
Project Management: Storm King Special Projects/Gabe Matherly
Contractor: Mullenax Roofing
Last Updated: September 23, 2021 07:20

This project will remove the cedar shakes and resurface the mansard with standing-seam metal roofing.


Exterior Painting

Estimated Cost: $38,000
Funding Source: Special Assessment
Current Status: Substantial completion.
Estimated Construction Time: July 1-31 (4 weeks, weather permitting)
Architect/Design Consultant: JHDesign
Project Management: Storm King Special Projects/Gabe Matherly
Contractor: Talingo’s Painting
Last Updated: September 23, 2021 07:22

This project will clean and repaint the building exterior.


Carpet Replacement

Estimated Cost: $40,000
Funding Source: Special Assessment
Current Status: Complete.
Estimated Construction Time: September 16-27 (2 weeks)
Architect/Design Consultant: JHDesign/Storm King Special Projects
Project Manager: Gabe Matherly
Contractor: TBA
Last Updated: September 23, 2021 07:24

This project will replace the carpet and repair certain subfloor sections throughout the common areas.


Interior Painting

Estimated Cost: $27,000
Funding Source: Special Assessment
Current Status: Complete.
Estimated Construction Time: Early September 2019 (2.5 weeks)
Architect/Design Consultant: JHDesign/Storm King Special Projects
Project Manager: Gabe Matherly
Contractor: TBA
Last Updated: September 23, 2021 07:25

This project will repair walls and repaint the building interior common areas.


Boiler Replacement

Estimated Cost: $96,111.00
Funding Source: SA
Current Status: Complete.
Estimated Construction Time: May 17 2017 through May 31 2017
Architect/Design Consultant: GMAPM
Project Manager: Gabe Matherly
Contractor: Clearwater Plumbing
Last Updated: August 2, 2017 06:19

This project will install/replace/upgrade:

  • Installation of air separator/remover
  • Installation of new flue & venting
  • Installation of new variable speed circulation pumps
  • New boiler electrical
  • New natural gas piping
  • Replacement of current boiler with three new high-efficiency boilers.
  • Replace two domestic hot water heaters
  • Systems integration

Elevator Modernization

Estimated Cost: $85,829.49
Funding Source: CBL
Current Status: Complete.
Estimated Construction Time: September 19 2016 through October 14 2016
Architect/Design Consultant: Brendan Gibbons, Tony Franzese
Project Manager: Gabe Matherly
Contractor: Otis Elevator
Last Updated: October 15, 2016 05:41

This project will install/replace/upgrade:

  • ADA Floor Passing Chime
  • ADA Integrated Hands-free Phone
  • Braille Car Operating Panel/Jamb Signs
  • Car Landing/Leveling System
  • Car Operating Panel/Travel Lanterns
  • Digital Car Position Indicator
  • Elevator Control System
  • Hallway Call Button Stations
  • Hoistway Switches & Wiring
  • Infrared Door Detector
  • Main/Aux Car Station Interfaces
  • Motor Starter
  • New Traveling Cables
  • Permitting & Inspection
  • Refurbish Door Tracks & Hangars
  • Relocate Elevator Drive Unit to Newly Constructed Machine Room
  • Renovate Car/Lighting
  • Upgrade Emergency Operation

Renovate Laundry Area

Estimated Cost: $15,525.00
Funding Source: CBL
Current Status: Complete.
Estimated Construction Time: June 20 2016 through July 22 2016
Architect/Design Consultant: Rob Classen
Project Manager: Gabe Matherly
Contractor: Daybreak Construction
Last Updated: July 20, 2016 08:22

This project includes:

  • New Paint, Flooring, & Trim
  • Replacing Gas Lines
  • Replacing Plumbing
  • Replacing Electrical
  • Upgrading Dryer Venting

Construct Machine Room

Estimated Cost: $22,685.00
Funding Source: CBL
Current Status: Complete.
Estimated Construction Time: July 25 2016 through August 31 2016
Architect/Design Consultant: Rob Classen
Project Manager: Dana Yerian, Gabe Matherly
Contractor: Daybreak Construction
Last Updated: August 20, 2016 08:50

This project includes:

  • Construction of Machine Room
  • Design and Finishing
  • Fireproofing
  • Installation of New Electrical Service
  • Installation of Lighting
  • Installation of HVAC per Engineering Requirements
  • Permitting & Inspection

Replace Fire Detection and Alarm System

Estimated Cost: $42,000.00
Funding Source: CBL/General Operating Fund
Current Status: Complete.
Estimated Construction Time: September 19 2016 through October 28 2016
Architect/Design Consultant: CWSI, GSFD
Project Manager: Gabe Matherly
Contractor: Vision Security
Last Updated: September 24, 2016 07:33

This project includes:

  • Installation of New Heat Detectors in Boiler and Machine Rooms
  • Installation of Bedroom Smoke Detectors
  • Installation of In-Unit Siren & Strobe Devices
  • Installation of Photo Thermal Detectors in Common Areas
  • Replacement of Fire Alarm Control Panel and Related Wiring
  • Installation of Annunciator at Main Entry
  • Replacement of Pull Stations
  • Replacement of Common Area Sirens/Strobes
  • Upgrading Central Monitoring Communications System
  • Permitting & Inspection

Renovate Bicycle Storage Room into Apartment

Estimated Cost: $46,725.00
Funding Source: Reserves/General Operating Fund
Current Status: Complete.
Estimated Construction Time: July 22 2016 through September 30 2016
Architect/Design Consultant: Rob Classen
Project Manager: Dana Yerian, Gabe Matherly
Contractor: Daybreak Construction
Last Updated: October 15 2016 05:19

This project includes:

  • Architectural Drawings
  • Construction of Kitchen
  • Construction of Bath
  • Construction of Bedroom
  • Design & Finishing
  • Electrical Design & Installation
  • Heating Retrofit
  • Permitting & Inspection
  • Tap Fees (W/WW)

Parking Lot Redesign

Estimated Cost: $2,500.00
Funding Source: General Operating Fund
Current Status: Preliminary Design
Estimated Construction Time: Late September 2017
Architect/Design Consultant: Rob Classen
Project Manager: Gabe Matherly
Contractor: TBD
Last Updated: May 2, 2017 09:03

This project will include:

  • Re-striping of Current Parking Area
  • Reconfiguration of Parking Lot Layout
  • Feasibility of Additional Parking at East Entrance

Basement Electrical Service Upgrade

Estimated Cost: $9,500.00
Funding Source: General Operating Fund
Current Status: Complete.
Estimated Construction Time: June 30 through July 6 2016
Architect/Design Consultant: Gavin Baucher
Project Manager: Gabe Matherly
Contractor: R&A Enterprises
Last Updated: July 20 2016 20:06

This project will include:

  • New Mechanical Room Service Panel
  • New Elevator Service Disconnect
  • New Mechanical Room Lighting
  • New Laundry Room Service & Lighting
  • GFCI Retrofit
  • Installation of Elevator Shaft Sump Pump
  • Permitting & Inspection

Basement Signing

Estimated Cost: $2,250.00
Funding Source: General Operating Fund
Current Status: Complete.
Estimated Construction Time: October 2016
Architect/Design Consultant: HSI
Project Manager: Gabe Matherly
Contractor: GMAPM
Last Updated: October 16, 2016 14:44

This project will include:

  • New Directional Signs in Lower Level
  • New Elevator Cab Signage
  • New Elevator Landings Signage
  • New Mechanical Room Signs

Note: The information presented here is subject to change, contains estimates, and may be incomplete. HHPOA will not be held liable for damages resulting from reliance on the information presented.